Maple Street Bottleneck Reduction Project 2024

You will find news and information about the town's Maple Street Bottleneck Reduction Project here.  Check back for updates. Contact Town Planner Katrina O'Leary for more information at: katrina.oleary@middletonma.gov

DATE
UPDATE
March 2023Grant application is submitted to the Bottleneck Reduction Program.  Recipients will receive up to $500K in construction funds plus MassDOT will use one of their engineering firms to design plans to address the stated concerns.
July 25, 2024Town receives notice that they have been selected to advance to the next step of the selection process and be visited by a MassDOT design consultant to verify the scope of the project.
October 31, 2023Nitsch Engineering submits a draft scope of services to MassDOT for approval
February 1, 2024The Town receives word via Nitsch Engineering that MassDOT has approved the draft scope of work and Nitsch Engineering is free to begin design according to the approved scope